Note:
The route corridors shown on this map are for general location purposes only. They are approximate and do not represent the actual design.
Project Description
The proposed road development includes the realignment of 3.6km of the N60 at Heathlawn approximately 1Km east of Balla.
The proposed road development includes the following;
3.6km of Type 2 Single Carriageway road (both online & offline).
Construction of a Cycleway
Local road realignments & Junction Improvements
Current Project Phase
The project is currently at Phase 6 (Construction) of the TII Project Management Guidelines. Construction commenced in November 2022 with the overall project expected to take 21 months to complete.